UIN 51669

National Grid: Feltham and Heston

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

20 September 2022

Last action

23 September 2022 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

23 September 2022

Summary

To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment his Department has made of the impact of capacity issues at the national grid on housebuilding in Feltham and Heston.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 20 September 2022

    Written question

    To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment his Department has made of the impact of capacity issues at the national grid on housebuilding in Feltham and Heston.

    Source: Commons

  2. 23 September 2022

    Answer

    The Government is aware of lengthy connection timelines currently being offered in parts of the country, particularly where transmission network upgrades are required to accommodate distribution network connections, such as housing developments. Network c...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.