To ask the Secretary of State for Levelling Up, Housing and Communities, what assessment he has made of the number of approved Building Safety Fund applications whose construction costs have risen since the initial tender was completed, and if he will tak

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 20 September 2022

    Written question

    To ask the Secretary of State for Levelling Up, Housing and Communities, what assessment he has made of the number of approved Building Safety Fund applications whose construction costs have risen since the initial tender was completed, and if he will tak

    Source: Commons

  2. 28 September 2022

    Answer

    Applicants can only submit a full costs application to the Building Safety Fund once they have gone out to tender and have a preferred contractor to carry out the remediation works. At that point they must provide the required cost breakdown and their app...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.