To ask the Secretary of State for Transport, what steps South Western Railways have taken to complete planned infrastructure upgrades including West of England line resilience works, London Waterloo-Clapham Junction and Fareham-Havant and Portsmouth Harbo

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 1 June 2026

    Written question

    To ask the Secretary of State for Transport, what steps South Western Railways have taken to complete planned infrastructure upgrades including West of England line resilience works, London Waterloo-Clapham Junction and Fareham-Havant and Portsmouth Harbo

    Source: Commons

  2. 9 June 2026

    Answer

    South Western Railway and Network Rail Wessex are delivering a coordinated programme of works by March 2027. This includes track improvements in Portsmouth as well as the strengthening of Portcreek Viaduct, and commencement of the £120 million Havant resi...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.