To ask the Secretary of State for Transport, how much power HS2 trains will need to run across each of the phases.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 15 October 2021

    Written question

    To ask the Secretary of State for Transport, how much power HS2 trains will need to run across each of the phases.

    Source: Commons

  2. 26 October 2021

    Answer

    We estimate that the HS2 network will require approximately 1 TWh of energy per annum at the completion of Phase 1/2a, and approximately a total of 2.5 TWh at the completion of Phase 2b. This will be subject to power usage specification of the Rolling Sto...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.