Summary

To ask the Secretary of State for Defence, if he will make an estimate of the potential impact of the time taken to deliver SKYNET 6A's launch on the value of the Service Delivery Wrap PFI awarded to Team Aurora.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 4 October 2024

    Written question

    To ask the Secretary of State for Defence, if he will make an estimate of the potential impact of the time taken to deliver SKYNET 6A's launch on the value of the Service Delivery Wrap PFI awarded to Team Aurora.

    Source: Commons

  2. 16 October 2024

    Answer

    The single event integration costs for Skynet 6A are factored into the overall contract price for the Service Delivery Wrap and that is unaffected by any movement in the launch date.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.