United Kingdom · Question · Written question
UIN 6805
Hinkley Point C Power Station
Introduced
23 May 2022
Last action
26 May 2022 · Answer
Status
Answered
Sponsors
—
Subjects
Discovery layer
Source updated
26 May 2022
Summary
To ask the Secretary of State for Business, Energy and Industrial Strategy, what the revised estimated dates are for the commissioning of Hinkley Point C (a) reactor one and (b) reactor two; and whether there is any estimated additional programme risk on
This text is taken from the official record. PoliticalRepo does not editorialize.
Timeline
23 May 2022
Written question
To ask the Secretary of State for Business, Energy and Industrial Strategy, what the revised estimated dates are for the commissioning of Hinkley Point C (a) reactor one and (b) reactor two; and whether there is any estimated additional programme risk on
Source: Commons
26 May 2022
Answer
EDF updated the forecast cost and schedule for Hinkley Point C on 19 May 2022. The forecast shows a Unit 1 Commercial Operation Date (COD) of June 2027 (12 months later than the current baseline schedule). Unit 2 is forecast to start 12 months after Unit ...
Source: Written answer
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
No documents linked.
Sponsors
- · Department for Business, Energy and Industrial Strategy · Answering body
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://questions-statements.parliament.uk/written-questions/detail/2022-05-23/6805
- Open data entity: https://questions-statements-api.parliament.uk/api/writtenquestions/questions/1465157
- uk · wq-1465157 · source updated 26 May 2022