Hinkley Point C Power Station

answeredUnited Kingdom· UK Parliament· EN

Introduced

23 May 2022

Last action

26 May 2022 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

26 May 2022

Summary

To ask the Secretary of State for Business, Energy and Industrial Strategy, what the revised estimated dates are for the commissioning of Hinkley Point C (a) reactor one and (b) reactor two; and whether there is any estimated additional programme risk on

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 23 May 2022

    Written question

    To ask the Secretary of State for Business, Energy and Industrial Strategy, what the revised estimated dates are for the commissioning of Hinkley Point C (a) reactor one and (b) reactor two; and whether there is any estimated additional programme risk on

    Source: Commons

  2. 26 May 2022

    Answer

    EDF updated the forecast cost and schedule for Hinkley Point C on 19 May 2022. The forecast shows a Unit 1 Commercial Operation Date (COD) of June 2027 (12 months later than the current baseline schedule). Unit 2 is forecast to start 12 months after Unit ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.