To ask the Secretary of State for Transport, what (a) financial viability and (b) risk assessments his Department has undertaken on major HS2 Ltd contractors on Phase 1 of High Speed Two following (a) Carillion going into administration and (b) the covid-

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 6 July 2020

    Written question

    To ask the Secretary of State for Transport, what (a) financial viability and (b) risk assessments his Department has undertaken on major HS2 Ltd contractors on Phase 1 of High Speed Two following (a) Carillion going into administration and (b) the covid-

    Source: Commons

  2. 9 July 2020

    Answer

    a) HS2 Ltd’s Supply Chain Management (SCM) function undertakes daily financial and capacity risk monitoring for all HS2 critical & strategic economic operators and their parent organisations during tendering and throughout contract delivery, at a Tier 1 a...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.