Summary

To ask the Secretary of State for Defence, how many working hours each week are provided by staff from (a) Bechtel, (b) PwC and (c) CH2M Hill under the managed service provider contracts to facilitate Defence Equipment and Support's transition to a tradin

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 15 July 2015

    Written question

    To ask the Secretary of State for Defence, how many working hours each week are provided by staff from (a) Bechtel, (b) PwC and (c) CH2M Hill under the managed service provider contracts to facilitate Defence Equipment and Support's transition to a tradin

    Source: Commons

  2. 20 July 2015

    Answer

    The Bechtel and CH2M Hill Managed Service Provider (MSP) contracts are based on a standard working week of 40 hours and the PwC MSP contract has a 37 hour working week, although actual weekly hours worked will depend upon the needs of the programme.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.