Midland Main Line: Electrification

answeredUnited Kingdom· UK Parliament· EN

Introduced

2 September 2025

Last action

8 September 2025 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

8 September 2025

Summary

To ask the Secretary of State for Transport, further to the Answer of 1 September 2025 to Question 69372 on Midland Main Line: Electrification, what is her Department's estimate of the cost of completing electrification of the Midland Main Line to Notting

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 2 September 2025

    Written question

    To ask the Secretary of State for Transport, further to the Answer of 1 September 2025 to Question 69372 on Midland Main Line: Electrification, what is her Department's estimate of the cost of completing electrification of the Midland Main Line to Notting

    Source: Commons

  2. 8 September 2025

    Answer

    The Department’s most recent estimate to electrify the Midland Main Line to Nottingham and Sheffield was c. £1.5 billion, however, before the decision to pause the programme was confirmed, work was being undertaken by Network Rail to update their cost est...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.