United Kingdom · Question · Written question

UIN 7522

Network Rail: Biodiversity

answeredUnited Kingdom· UK Parliament· EN

Introduced

8 June 2026

Last action

18 June 2026 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

18 June 2026

Summary

To ask the Secretary of State for Transport, what estimate her Department has made of the total projected expenditure required by Network Rail to achieve a 4 per cent biodiversity net gain by December 2029; and how much of that funding has been formally a

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 June 2026

    Written question

    To ask the Secretary of State for Transport, what estimate her Department has made of the total projected expenditure required by Network Rail to achieve a 4 per cent biodiversity net gain by December 2029; and how much of that funding has been formally a

    Source: Commons

  2. 18 June 2026

    Answer

    It is not possible to separate the cost of achieving 4 per cent biodiversity net gain by December 2029 from the cost of general planned management activity on Network Rail’s estate, as progress towards biodiversity net gain is not a discrete activity with...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.