United Kingdom · Question · Written question

UIN 77840

High Speed 2 Line: Costs

answeredUnited Kingdom· UK Parliament· EN

Introduced

16 September 2025

Last action

14 October 2025 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

14 October 2025

Summary

To ask the Secretary of State for Transport, with reference to paragraph 2.18 of the National Audit Office report entitled High Speed Two: A progress update, published on 24 January 2020, whether HS2 Limited has updated its indicative estimate that the co

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 16 September 2025

    Written question

    To ask the Secretary of State for Transport, with reference to paragraph 2.18 of the National Audit Office report entitled High Speed Two: A progress update, published on 24 January 2020, whether HS2 Limited has updated its indicative estimate that the co

    Source: Commons

  2. 14 October 2025

    Answer

    HS2 Ltd has not updated this figure. The estimate was provided to the National Audit Office in late 2019 – at that time, HS2 Ltd’s cost estimates were in 2015 prices.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.