To ask the Secretary of State for Defence, what recent progress he has made on implementing a new non-tidal maintenance berth as part of the Submarine Waterfront Infrastructure Future project.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 10 October 2025

    Written question

    To ask the Secretary of State for Defence, what recent progress he has made on implementing a new non-tidal maintenance berth as part of the Submarine Waterfront Infrastructure Future project.

    Source: Commons

  2. 17 October 2025

    Answer

    The Submarine Waterfront Infrastructure Future (SWIF) programme will provide facilities to locations such as Devenport that include a new non-tidal maintenance berth in 5 Basin, a refurbished 10 Dock, and supporting buildings and services. Significant pla...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.