AWE Burghfield: Construction

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

10 October 2025

Last action

17 October 2025 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

17 October 2025

Summary

To ask the Secretary of State for Defence, if he will set out the remaining (a) scope and (b) cost to completion for the MENSA programme.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 10 October 2025

    Written question

    To ask the Secretary of State for Defence, if he will set out the remaining (a) scope and (b) cost to completion for the MENSA programme.

    Source: Commons

  2. 17 October 2025

    Answer

    The MENSA programme continues to make progress and is nearing the end of its construction and commissioning stage. As set out in the National Infrastructure and Service Transformation Authority Annual Report 2024-25, the latest cost estimate to deliver th...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.