United Kingdom · Question · Written question

UIN 8079

M25: Repairs and Maintenance

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

8 October 2024

Last action

16 October 2024 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

16 October 2024

Summary

To ask the Secretary of State for Transport, pursuant to the Answer of 8 October 2024 to Question 5795 on M25: Noise, when Next Generation Concrete Surfacing will take place between Junctions 8 and 9 on the M25.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 October 2024

    Written question

    To ask the Secretary of State for Transport, pursuant to the Answer of 8 October 2024 to Question 5795 on M25: Noise, when Next Generation Concrete Surfacing will take place between Junctions 8 and 9 on the M25.

    Source: Commons

  2. 16 October 2024

    Answer

    A section of the M25 between Junction 8 and Junction 9 was treated with Next Generation Concrete Surfacing (NGCS) in September 2024 and wider implementation of NGCS on the M25 is expected to be undertaken from 2026. At present, National Highways is unable...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.