Summary

To ask the Secretary of State for Transport, pursuant to the Answer of 5 June 2026 to Question 3549 on High Speed 2 Line, when she expects the updating of the HS2 programme business case and the resetting of the benefits baseline to be completed; and whet

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 9 June 2026

    Written question

    To ask the Secretary of State for Transport, pursuant to the Answer of 5 June 2026 to Question 3549 on High Speed 2 Line, when she expects the updating of the HS2 programme business case and the resetting of the benefits baseline to be completed; and whet

    Source: Commons

  2. 17 June 2026

    Answer

    DfT and HS2 Ltd are currently in the process of updating the programme business case and resetting the benefits baseline in line with the ongoing programme reset, which should be complete by Spring 2027. The programme benefits and how HS2 will realise the...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.