To ask the Secretary of State for Science, Innovation and Technology, how many and what proportion of properties have been connected to full fibre under the North Shropshire Project Gigabit contract.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 14 October 2025

    Written question

    To ask the Secretary of State for Science, Innovation and Technology, how many and what proportion of properties have been connected to full fibre under the North Shropshire Project Gigabit contract.

    Source: Commons

  2. 20 October 2025

    Answer

    As of 25 June 2025, Freedom Fibre delivered 2,500 out of an original contract of 12,000 premises, for a proportion of 21% of the original contract. Building Digital UK will publish more up-to-date data about contract delivery in the next few weeks.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.