United Kingdom · Question · Written question

UIN 8208

Housing: Northstowe

answeredUnited Kingdom· UK Parliament· EN

Introduced

9 October 2024

Last action

18 October 2024 · Answer

Status

Answered

Sponsors

Subjects

Housing

Source updated

18 October 2024

Housing

Summary

To ask the Secretary of State for Housing, Communities and Local Government, Pursuant to the answer of 25 July 2024, to Question 1010 on Housing: Northstowe, what the site specific reasons that the project was stalled are.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 9 October 2024

    Written question

    To ask the Secretary of State for Housing, Communities and Local Government, Pursuant to the answer of 25 July 2024, to Question 1010 on Housing: Northstowe, what the site specific reasons that the project was stalled are.

    Source: Commons

  2. 18 October 2024

    Answer

    The New Homes Accelerator, in partnership with Homes England, will support the delivery of Phase 2 of the Northstowe scheme in Cambridgeshire, unlocking 3,000 homes and continuing to progress proposals to unlock a further 2,600 homes in Phase 3.As a resul...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.