Data Centres: Electricity

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

9 June 2026

Last action

17 June 2026 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

17 June 2026

Summary

To ask the Secretary of State for Energy Security and Net Zero, what proportion of electricity demand connection applications in the National Energy System Operator queue are attributable to data centres.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 9 June 2026

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, what proportion of electricity demand connection applications in the National Energy System Operator queue are attributable to data centres.

    Source: Commons

  2. 17 June 2026

    Answer

    Data supplied by the National Energy System Operator shows around 60GW of capacity allocated to data centres in the transmission queue. This represents around three quarters of the total demand connections queue, at transmission level. Government recently...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.