High Speed 2 Line: Land

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

8 November 2023

Last action

13 November 2023 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

13 November 2023

Summary

To ask the Secretary of State for Transport, what estimate he has made of the amount his Department spent on (a) land acquisition and (b) compensation for Phase (i) 2a and (ii) 2b of HS2 from 20 July to 4 October 2023.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 November 2023

    Written question

    To ask the Secretary of State for Transport, what estimate he has made of the amount his Department spent on (a) land acquisition and (b) compensation for Phase (i) 2a and (ii) 2b of HS2 from 20 July to 4 October 2023.

    Source: Commons

  2. 13 November 2023

    Answer

    It is not practicable to make a precise division between land, property and businesses, as many property titles will encompass a combination of these. During the calendar months of August and September 2023, £11,770,997 was committed in relation to Phase ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.