Summary

To ask the Secretary of State for Transport, what the total rail enhancement funding available to Network Rail for Control Period 6 is; what the actual spend is in years (a) one and (b) two; and what the forecast total spend is for years (i) three, (ii) f

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 27 May 2021

    Written question

    To ask the Secretary of State for Transport, what the total rail enhancement funding available to Network Rail for Control Period 6 is; what the actual spend is in years (a) one and (b) two; and what the forecast total spend is for years (i) three, (ii) f

    Source: Commons

  2. 7 June 2021

    Answer

    The budget for Rail Enhancements for England and Wales during Control Period 6 (CP6, 2019/20-23/24) is £9.4 Billion. The actual spend in years requested was:(a) one (2019/20) = £1,475 Million(b) two (2020/21) = £1,477 Million The latest forecast spend (Ne...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.