To ask the Secretary of State for Transport, when he expects work on the A12 widening scheme to begin and to be completed.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 1 February 2024

    Written question

    To ask the Secretary of State for Transport, when he expects work on the A12 widening scheme to begin and to be completed.

    Source: Commons

  2. 8 February 2024

    Answer

    National Highways set out its expected delivery schedule on the A12 Chelmsford to A120 widening scheme (junctions 19 to 25) in its Delivery Plan Update, with start of works expected in 2023/24 and open for traffic in Road Period 3 (2025-2030). National H...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.