Broadband: North Herefordshire

Original

answeredUnited Kingdom· UK Parliament· EN

Introduced

13 November 2025

Last action

21 November 2025 · Answer

Status

Answered

Sponsors

Subjects

Discovery layer

Source updated

21 November 2025

Summary

To ask the Secretary of State for Science, Innovation and Technology, what steps she is taking to provide timelines to North Herefordshire constituents on when they will be able to access a gigabit-capable broadband connection, in the context of the delay

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 13 November 2025

    Written question

    To ask the Secretary of State for Science, Innovation and Technology, what steps she is taking to provide timelines to North Herefordshire constituents on when they will be able to access a gigabit-capable broadband connection, in the context of the delay

    Source: Commons

  2. 21 November 2025

    Answer

    As part of Project Gigabit, Openreach is contracted to provide gigabit-capable broadband to approximately 3,050 premises in the North Herefordshire constituency that are not included in suppliers’ commercial plans. This coverage is contracted to be comple...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.