To ask the Secretary of State for Transport, what estimate he has made of the change in the amount of granite that will be mined as a result of the cancellation of the northern leg of HS2.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 November 2023

    Written question

    To ask the Secretary of State for Transport, what estimate he has made of the change in the amount of granite that will be mined as a result of the cancellation of the northern leg of HS2.

    Source: Commons

  2. 16 November 2023

    Answer

    No granite would have been mined for the construction of the Phase 2 route from Birmingham to Manchester because granite does not occur naturally in the ground along the chosen route

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.