Summary

To ask the Secretary of State for Defence, with reference to his Department's press release entitled Storage facility for over 900 vehicles completed at MOD Ashchurch, published on 5 March 2025, when all 13 new buildings will be delivered as part of the V

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 2 December 2025

    Written question

    To ask the Secretary of State for Defence, with reference to his Department's press release entitled Storage facility for over 900 vehicles completed at MOD Ashchurch, published on 5 March 2025, when all 13 new buildings will be delivered as part of the V

    Source: Commons

  2. 10 December 2025

    Answer

    The Vehicle Storage and Support Programme (VSSP) remains on schedule and work at MOD Ashchurch will be completed in 2027. Demolition of all 58 existing buildings as part of the VSSP, has been completed.

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.