United States · Bill · S
S. 1972 (110th)
A bill to amend the Federal Power Act to modify a provision relating to the siting of interstate electric transmission.
Introduced
2 August 2007
Last action
—
Status
Read twice and referred to the Committee on Energy and Natural Resources.
Sponsors
—
Subjects
Discovery layer
Source updated
24 March 2026
Summary
Amends the Federal Power Act to authorize the Federal Energy Regulatory Commission (FERC) to issue a construction permit for siting an interstate electric transmission facility if it finds that an authorized state entity has: (1) approved the siting of the proposed facility; or (2) unreasonably withheld a determination, or delayed making a determination, for a period of at least two years after the date on which the permit application was filed. Repeals provisions governing: (1) rights-of-way; and (2) compensation for acquisition of rights-of-way. Prohibits FERC from issuing a permit if a state entity has denied a permit application for the same project during the two-year period beginning on the date the permit application is submitted to the entity.
This text is taken from the official record. PoliticalRepo does not editorialize.
Timeline
No timeline events have been ingested for this record yet.
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
3 official files
Introduced in Senate (text)
Introduced in Senate · EN · 2 August 2007
Introduced in Senate (PDF)
Introduced in Senate · EN · 2 August 2007
Introduced in Senate
summary · EN · 2 August 2007
Sponsors
No sponsors or actors listed by the source.
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://www.congress.gov/bill/110th-congress/senate-bill/1972
- Open data entity: https://api.congress.gov/v3/bill/110/s/1972