United Kingdom · Question · Written question
UIN 160097
Nuclear Power Stations: Construction
Introduced
7 March 2023
Last action
15 March 2023 · Answer
Status
Answered
Sponsors
—
Subjects
Nuclear energy
Source updated
15 March 2023
Summary
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of how long it will take to place contracts to build new smaller nuclear power stations.
This text is taken from the official record. PoliticalRepo does not editorialize.
Timeline
7 March 2023
Written question
To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of how long it will take to place contracts to build new smaller nuclear power stations.
Source: Commons
15 March 2023
Answer
The Government is committed to ensuring that the UK is one of the best places in the world to invest in new nuclear and intends to take one project to Final Investment Decision (FID) this Parliament and two projects to FID in the next Parliament, includin...
Source: Written answer
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
No documents linked.
Leesvertaling
Vertaal dit document naar jouw taal. PoliticalRepo bewaart geen aparte kopie per EU-taal.
Documentvertaling op verzoek met downloadbare PDF (logo + link naar de officiële bron). Het bronbestand blijft leidend.
Sponsors
- · Department for Energy Security and Net Zero · Answering body
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://questions-statements.parliament.uk/written-questions/detail/2023-03-07/160097
- Open data entity: https://questions-statements-api.parliament.uk/api/writtenquestions/questions/1602044
- uk · wq-1602044 · source updated 15 March 2023