PoliticalRepoPoliticalRepo

United Kingdom · Question · Written question

UIN 22917

Energy: Payments

answeredUnited Kingdom· UK Parliament· EN

Introduced

22 April 2024

Last action

25 April 2024 · Answer

Status

Answered

Sponsors

Subjects

Energy

Source updated

25 April 2024

Energy

Summary

To ask the Secretary of State for Energy Security and Net Zero, with reference to the Answer of 27 March 2024 to Question 19567, (a) on how many days and (b) for how many hours energy companies were asked to (i) curtail and (ii) increase generation as a r

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 22 April 2024

    Written question

    To ask the Secretary of State for Energy Security and Net Zero, with reference to the Answer of 27 March 2024 to Question 19567, (a) on how many days and (b) for how many hours energy companies were asked to (i) curtail and (ii) increase generation as a r

    Source: Commons

  2. 25 April 2024

    Answer

    National Grid ESO manages network constraints. In 2023, constraint costs were £1.4bn and the volume of balancing services used to manage constraints was around 12TWh. Data are not available on exact timing of curtailment and the split of costs between ren...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.