United Kingdom · Question · Written question
UIN 30878
National Grid
Introduced
9 October 2026
Last action
19 October 2026 · Answer
Status
Answered
Sponsors
—
Subjects
Energy
Source updated
19 October 2026
Summary
To ask the Secretary of State for Energy Security and Net Zero, how many transmission-connected demand projects have received Gate 2 offers under the Gate 2 to Whole Queue process; how many are data centres; and what the earliest and latest connection dat
This text is taken from the official record. PoliticalRepo does not editorialize.
Timeline
9 October 2026
Written question
To ask the Secretary of State for Energy Security and Net Zero, how many transmission-connected demand projects have received Gate 2 offers under the Gate 2 to Whole Queue process; how many are data centres; and what the earliest and latest connection dat
Source: Commons
19 October 2026
Answer
The National Energy System Operator (NESO) is currently implementing the Gate 2 to Whole Queue process and connection offers continue to be issued. Data collected in 2025 and published by NESO shows 72.8 GW of capacity allocated to data centres in the GB ...
Source: Written answer
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
2 official files
Leesvertaling
Vertaal dit document naar jouw taal. PoliticalRepo bewaart geen aparte kopie per EU-taal.
Documentvertaling op verzoek met downloadbare PDF (logo + link naar de officiële bron). Het bronbestand blijft leidend.
Answer
text · EN · 19 October 2026
Question
text · EN · 9 October 2026
Leesvertaling
Vertaal dit document naar jouw taal. PoliticalRepo bewaart geen aparte kopie per EU-taal.
Documentvertaling op verzoek met downloadbare PDF (logo + link naar de officiële bron). Het bronbestand blijft leidend.
Sponsors
- · Department for Energy Security and Net Zero · Answering body
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://questions-statements.parliament.uk/written-questions/detail/2026-10-09/30878
- Open data entity: https://questions-statements-api.parliament.uk/api/writtenquestions/questions/1944699
- uk · wq-1944699 · source updated 19 October 2026