UIN 71352

Baglan Energy Park: Energy Supply

answeredUnited Kingdom· UK Parliament· EN

Introduced

8 November 2021

Last action

22 November 2021 · Answer

Status

Answered

Sponsors

Subjects

Energy

Source updated

22 November 2021

Energy

Summary

To ask the Secretary of State for Business, Energy and Industrial Strategy, what estimate he has made of the monthly cost of maintaining the energy supply to Baglan Energy Park after 30 November 2021.

This text is taken from the official record. PoliticalRepo does not editorialize.

Timeline

  1. 8 November 2021

    Written question

    To ask the Secretary of State for Business, Energy and Industrial Strategy, what estimate he has made of the monthly cost of maintaining the energy supply to Baglan Energy Park after 30 November 2021.

    Source: Commons

  2. 22 November 2021

    Answer

    I am advised by the Official Receiver, who was appointed as liquidator as of 24 March 2021 of the Baglan Group, including Calon Energy (Baglan Bay) Ltd, Baglan Generating Ltd, Baglan Operations Ltd and Baglan Pipeline Ltd, that the estimated monthly cost ...

    Source: Written answer

Votes

No vote records are attached yet.

Versions

No version snapshots stored. Document URLs remain at the source.

Documents

No documents linked.

Sponsors

Related records

No cross-record relationships stored yet.

Sources

PoliticalRepo is an index and interpretation layer, not the authoritative legal source.