In March 2025, the Secretary of State for Energy Security and Net Zero commissioned the North Hyde Substation Review, an independent report delivered by the National Energy System Operator (NESO). The report was commissioned following a large fire breakin...
This text is taken from the official record. PoliticalRepo does not editorialize.
Timeline
2 July 2025
Written statement
In March 2025, the Secretary of State for Energy Security and Net Zero commissioned the North Hyde Substation Review, an independent report delivered by the National Energy System Operator (NESO). The report was commissioned following a large fire breakin...
Source: Commons
Votes
No vote records are attached yet.
Versions
No version snapshots stored. Document URLs remain at the source.
Documents
No documents linked.
Leesvertaling
Vertaal dit document naar jouw taal. PoliticalRepo bewaart geen aparte kopie per EU-taal.
Documentvertaling op verzoek met downloadbare PDF (logo + link naar de officiële bron). Het bronbestand blijft leidend.
Sponsors
- · Department for Energy Security and Net Zero · Answering body
Related records
No cross-record relationships stored yet.
Sources
PoliticalRepo is an index and interpretation layer, not the authoritative legal source.
- Official source: https://questions-statements.parliament.uk/written-statements/detail/2025-07-02/HCWS770
- Open data entity: https://questions-statements-api.parliament.uk/api/writtenstatements/statements/1818613
- uk · ws-1818613 · source updated 2 July 2025